- The construction project included the upgrading of the Northern Railway (line 6088) between Neustrelitz and Neubrandenburg.
- Construction period mid-March 2024 – beginning of July 2024
- Total length of the construction project on 32 km
- Extensive track renewals were carried out, including ballast and subgrade protection layer renewals to increase the line speed to 120 km/h over a length of 11 km
- 8 new culverts were built as well as dismantling and grouting of the old culverts
- Creation of edge and rescue routes
- Reprofiling and new construction of railway ditches
Your contact person
Although the three municipalities may be close to each other, it is still important to ensure a smooth networking of the people in the region.
As a track construction specialist, it does not matter to us whether the route to be worked on is long-distance or regional: the track remains the track. And since rail transport plays an important role in passenger and goods transport in the long term, the best quality is the absolute standard in each of our projects. The special feature here: Our new Stopfexpress 09-3X, which we received at the iaf 2017, celebrated its first use here.
David Schmitter (Abteilungsleiter Gleisbau)
Phone: +49 (0)4202 – 987-294
E-mail: DSchmitter@wiebe.de
Kai Legenhausen (Managing Director)
Phone: +49 (0)4202 – 987-0
Fax: +49 (0)4202 – 987-100
E-mail: KLegenhausen@wiebe.de
If you have any questions, we will be happy to help you.
or call us: