Construction of a prefabricated platform in Saulgrub on the DB line Murnau – Oberammergau
Service description:
Saulgrub station on the DB line Murnau – Oberammergau was to be made barrier-free. For this purpose, the existing conventional platform was raised from 55 cm to 76 cm above the top of the rails. The modular platform system MBS-SB was used for this purpose. A levelling layer was applied to the existing platform surface as a support for the prefabricated platform slabs.
By using this platform system, the measure could be completed after only one week of construction.
Client:
DB Station & Service AG, Munich
Period:
From April 2020 to May 2020
Technical specifications:
Type of structure: Precast platform type MBS-SB, precast panels
Length: 80 m
Width: 2.65 m
Foundation: Placing the precast panels on the existing surface
Contract amount: approx. 450,000 €
Project images
Start of the renovation
The completed Saulgrub platform
Your contact person
Although the three municipalities may be close to each other, it is still important to ensure a smooth networking of the people in the region.
As a track construction specialist, it does not matter to us whether the route to be worked on is long-distance or regional: the track remains the track. And since rail transport plays an important role in passenger and goods transport in the long term, the best quality is the absolute standard in each of our projects. The special feature here: Our new Stopfexpress 09-3X, which we received at the iaf 2017, celebrated its first use here.
David Schmitter (Head of Track Construction)
Phone: +49 (0)4202 – 987-294
E-mail: DSchmitter@wiebe.de
Kai Legenhausen (Managing Director)
Phone: +49 (0)4202 – 987-0
Fax: +49 (0)4202 – 987-100
E-mail: KLegenhausen@wiebe.de
If you have any questions, we will be happy to help you.
or call us: